Holt County Supervisors approved a change order for work on the Ewing Southeast project C45, on the St. John's bridge.
During the Nov. 18 meeting, road superintendent Gary Connot said Dixon Construction had planned to start construction Nov.4.
"They revised it initially for a couple weeks, Nov. 18, and they revised it again for a December start," Connot said.
Ramsy Robertson, engineer with Mainelli Wagner & Associates, reviewed the construction schedule with supervisors.
"It's up to you if you're okay with the change. Otherwise, we can start charging days today. They bid it working days," Robe...